UNIT NO. 7 AT NAZAROVSKAYA GRES OF SIBERIAN GENERATING COMPANY WAS PUT ON TRIAL POWER SUPPLY.

Nazarovskaya GRES, as part of the project on technical re-equipment of power unit No. 7, started testing of the equipment under load, with trial powering of the unit into the grid in single-boiler mode, with boiler 7-A. This was preceded by completion of the main part of installation and preparatory works on boiler, turbine and electrical equipment. According to the commissioning plan, during testing in single-boiler mode it is planned to increase the capacity up to 250 MW.

See details in Portal Energyland

In this investment project EF-TEK LLC performs the functions of an expert to organize continuous control over the progress and quality of construction and commissioning works during construction (monitoring, analysis and preparation of reports on the progress of works from the beginning of construction of facilities to their commissioning).