Omskaya CHPP-5
Development of preliminary feasibility study on implementation of dry ash and slag waste disposal system
Country:
Russian Federation
Location:
Stavropol region
Customer:
MGES Stavropolya i KCHR, LLC
Period:
September 2017 - August 2018 (IPPP-1), September 2017 - October 2018 (IPPP-2)
Omskaya CHPP-5 (in operation since 1976) is the most powerful plant in the Omsk energy system, providing heat to the Central, Oktyabrsky and partially Leninsky and Kirovsky administrative districts of Omsk.
Installed electric capacity - 735 MW
Installed heat capacity - 1763 Gcal/h.
Within the framework of the performed works the expediency of restoration of infrastructure of existing sections of ash disposal area was estimated, the cost of such restoration was estimated.
For each of the considered variants of ash and slag handling and storage, dust suppression and reclamation the necessary equipment was selected and the main production indicators were determined.
For the options agreed with the customer, the cost of project implementation for dry relocation of ASW from the existing sections to the dry storage site and rehabilitation of the infrastructure of the existing sections was estimated.