Artemovskaya CHPP-2 is intended to replace retiring capacities of the existing Artemovskaya CHPP in order to ensure socio-economic development and sustainable energy supply to consumers in the Far Eastern Federal District.
Within the framework of the considered OBIN it is supposed to construct a power plant with an electric capacity of 400-500 MW, with a heat load of 325 Gcal/h.
The main fuel is brown coal from the Primorsky Krai deposit with calorific value of 2541 - 2885 kcal/kg.
The scope of services of EF-TEK LLC includes:
- Expert-engineering assessment of feasibility of costs for investment project realization
- Expert-engineering assessment of terms and schedule of investment project realization
- Expert-engineering evaluation of the feasibility of constructive, technical and estimated solutions
- Expert-engineering assessment of feasibility of technological solutions
- Identification of the main risks of the investment project