COMPREHENSIVE TESTING OF A NEW GENERATION BOILER UNIT BEGAN AT BARNAULSKAYA TPP-2

Barnaulskaya CHPP-2 (part of Siberian Generating Company Group) continues to implement a major investment project under a capacity delivery agreement (CDA).

Among the priority projects of the current year is the commissioning of the reconstructed boiler unit No. 12. Upon completion of all planned installation works, the power engineers started its commissioning tests.

See more on Portal Energyland

In this investment project EF-TEK LLC performs the functions of an expert in order to organize continuous control over the progress and quality of construction and commissioning works during construction (monitoring, analysis and preparation of reports on the progress of works from the beginning of construction of facilities to their commissioning).